[Math] Integration — Work done in pulling an elevator using a rope

integrationphysics

An elevator weighing $3000$ lbs. is supported by a $12$ ft. cable that weights $14$ lbs./ft. Find the work a winch has to do by pulling the rope to lift the elevator $9$ feet.

I eventually figured out how to do this problem as follows:
$$
9 (3000+3\cdot 14) + \int_3^{12} 14 (12-y) \, \mathrm{d}y
$$

where since the elevator only moving 9ft the bottom 3ft of the cable can be considered part of the elevator weigh so the combined weight that must be pulled a fixed distance of $9$ feet is $(3000 + 3 \cdot 14)$ lbs.


However, I also found that the following integral also gives the correct answer:
$$
9\cdot 3000 + \int_0^9 14 (12-y) \, \mathrm{d}y
$$

However I cannot understand why this integral also works, as when you slice the rope into vertically stacked discs the above integral posits that the bottom most slice moves $12$ feet, which cannot be right.

Could someone please explain visually how the second integral calculates the work done?

Best Answer

The bounds of the integral are being passed to (12-y), so smaller y results in larger areas of integration.

The first equation seems easier to "visualize" to me too, but I think the second one can be intuited as well. The first term is the work done for the elevator. The second term is the work done for the cable as it moves from position zero to position nine. At the start, there are 12-0=12 units of cable, and as expected there will be 12-9=3 units remaining at the end.

I'm not sure exactly what you mean by 'the bottom disk must move by 12.'